Define what the factory closure must actually finish

Topic
Manufacturing site closure
Reading time
3 minutes
Last reviewed
On this page
  1. Five outcomes with different acceptance
  2. Write the unresolved boundaries into the brief
  3. Connect the scope to enquiries

Write down what "factory closed" means before agreeing a completion date. The last production run, the last quality decision and the end of property obligations may occur at different times. A single milestone can hide the work between them.

The owner needs a scope that advisers and contractors can assess. Keep technical methods and legal conclusions with the relevant specialists. A management scope statement coordinates their work; it does not replace it.

Five outcomes with different acceptance

Use the actual roles in your business. The following example separates decisions that can otherwise become mixed together.

Outcome What the closure programme must establish Acceptance to identify
Production stops Which work ends and what orders remain unresolved Operations and commercial owners
Quality work reaches an agreed outcome Who resolves held batches, tests and product enquiries Responsible quality authority
Decommissioning reaches its defined scope What competent specialists must assess, perform and document Relevant technical and project roles
Assets become available for the agreed disposal route Which items the business has authority to release and which dependencies remain Authorised commercial decision-maker with operational input
Property exit is completed What the actual lease, ownership or other arrangement requires Owner and property advisers with the relevant counterparty

One individual may contribute to several rows, but the decisions remain distinct. Selling an asset cannot answer a question about permit surrender. Finishing ordinary production cannot decide the fate of a held batch.

Write the unresolved boundaries into the brief

A fictional scope statement might say:

Production at this site will end after the agreed order review. The laboratory has outstanding testing whose completion date remains to be confirmed. The decommissioning scope needs technical assessment. The proposed sale excludes equipment still required for that testing. Property exit remains subject to the agreed advice and evidence.

The statement gives each person a defined outcome and an unresolved question to assess. Add named owners and the information needed to resolve the open points.

Use the area-status board to show how these decisions apply across the building. Different areas may reach different states during the same week.

Connect the scope to enquiries

Give a proposed contractor the relevant decommissioning brief, including interfaces and exclusions. Ask them to identify assumptions and work outside their proposal. Do not infer that one appointment covers every discipline or transfers every duty.

Discuss the asset-sale and clearance element with UK Auction Group. Their business closure page covers those services. Explain the factory's remaining operational dependencies and ask how the disposal scope could fit the wider programme.

Before the internal project team disperses, assign remaining site responsibilities. A task can continue beyond the target date, but it still needs an accountable person and an agreed way to fund and complete it.

See the manufacturing site closure guides.

Sources

This guide is general information and education only. Legal, tax, employment and safety decisions may need a qualified adviser who knows your situation. Read the disclaimer.

Closing a business with assets to sell?

UK Auction Group values everything on site, runs the sale and hands the premises back clear, with a full statement of proceeds at the end.

Send a list of what you have, where it is and your deadline. Decisions that are still open can be included.

Business closure auctions and site clearance Contact UK Auction Group

Business Closure Guide is part of the UK Auction Group portfolio.

Browse all guides by topic