Keep factory utility changes on one authorised programme
- Reading time
- 2 minutes
- Last reviewed
On this page
Give requests affecting factory services one recognised route through the responsible technical and business leads. Separate instructions from production, property and contractors can otherwise rely on incompatible assumptions about the same service.
The programme should record the agreed decision and its dependencies. It must not prescribe isolation steps or substitute for the competent planning and control of technical work.
Follow a request from purpose to accepted change
A fictional request says a service is no longer needed because one production area has stopped. Before it becomes a project instruction, the responsible team needs to establish what else depends on that service.
Record the request and each subsequent decision:
| Stage | Record to obtain |
|---|---|
| Request | Proposed outcome, reason and person requesting it |
| Dependency review | Activities, areas and other users that may be affected, with unresolved information identified |
| Specialist assessment | Required technical advice, applicable arrangements and responsible decision-makers |
| Business decision | Effect on remaining work and commitments, with appropriate authority |
| Accepted programme change | Defined scope, conditions and communication to affected parties |
| Completion and follow-up | Required evidence and any remaining restrictions or responsibilities |
The technical team decides what assessment and work arrangements are necessary. A completed row on this record is not a substitute for their acceptance.
Challenge the phrase "nobody uses it now"
Ask which activities the statement covers and who confirmed them. The service might still support testing, retained production, building arrangements or another business. Records may also contain unresolved changes that need specialist attention.
The area-status board identifies current use but should not be treated as a technical service map. A room being vacant does not prove all its connections are redundant.
Include the process-material decisions where relevant. The specialists may need to understand remaining contents and planned work before they can assess a service change.
Communicate the actual decision
Tell affected parties what has been accepted, what remains conditional and where the current record is held. Avoid circulating an early request as though it were an instruction to proceed.
If another organisation depends on the service, use the external dependency enquiry. Its agreement and continuity questions need their own resolution through the proper technical and legal routes.
Record superseded decisions clearly. A contractor working from an earlier programme needs to know which instruction changed and who can clarify it. The owner should ask how this communication is controlled within the project arrangements.
Give UK Auction Group the relevant confirmed constraints when discussing disposal. Equipment availability may depend on assessed service work; a proposed programme date should remain provisional until its conditions are met.